Sandøy

Number of windmills: 10-20
Output: 50-100 MW
Production: 100-200 GWh
Equivalent to the consumption of: approx. 10,000 households
Project status: Impact analysis ongoing, application for permit spring 2019

The project is located on the Sandøy island in the municipality of Gulen near to industrial areas and existing roads. The point of input to the grid and a usable pier are in the immediate vicinity, which means there is very limited requirements for new infrastructure.

Status

31. January 2020:

The turbine installation works are slowly but steadingly progressing and the half-way mark (35 installed turbines) was passed in the middle of January. 20 turbines at Eikeland-Steinsland are now completly installed, i.e. in total 38 completed turbines including Skinansfjellet wind farm.

The main cranes are expected to start installation at Gravdal wind farm in March and hopefully complete the last turbine in May.